The sequential order of construction phase is as follows:
  1. Design, construction administration, bidding, and occupancy
  2. Predesign, design, bidding, construction, and occupancy
  3. Predesign, design, construction, construction documents, and construction administration
  4. Design, bidding, construction and construction documents, and sale
Explanation
Answer - B - The sequential order of all phases is as follows; 1) predesign 2) design 3) bidding 4) construction/construction administration, and 5) occupancy. Construction documents typically occur during the design phase and construction administration occurs during the construction phase.