The Procurement Management Plan is an input to:
  1. Human Resource Planning
  2. Cost Estimating and Budgeting
  3. Program Management Plan
  4. Plan Program Purchases and Acquisitions
Explanation
Answer - C - The procurement management plan is an input to the Program Management Plan.

Key Takeaway: The Procurement Management Plan specifies how procurement processes will be performed in the life of a program. This plan includes the types of contracts that will be used, identifying prequalified sellers, procurement metrics to manage contracts and evaluate sellers, coordination with schedule and performance reporting, scheduled dates for deliverables, directions on developing and maintaining a contract WBS. The procurement management plan is an output of Program Purchases and Acquisitions and then acts as an input to the Program Management Plan.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz