Flogsworth Wort always forgets the inputs to the Quality Planning process. Which is NOT an input to the Quality Planning process?
  1. Product description
  2. Program scope statement
  3. Program cost of quality
  4. Regulation and legislation
Explanation
Answer - C - Program cost of quality is not an input of Quality Planning.

Key Takeaway: Quality planning is a process for setting parameters for how to identify a program’s quality standards and how the group will meet these standards. Because these guidelines have such a huge impact on critical program activities, it is crucial for Quality Planning to take place early in the life span of a program-ideally, right after defining the scope. Input items to Quality Planning are: the program scope statement, detailed description of the product, and a list of environmental factors relating to the program.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz