The Commissioning Plan includes all of the following information except:
  1. Schedule
  2. Allocation of resources
  3. Organization
  4. Team identification
Explanation
Answer - D - The commissioning team is not one of the items included in the Commissioning Plan. A Commissioning Plan is a document that outlines the organization, schedule, allocation of resources, and documentation requirements of the commissioning purpose.