Sally Akins is a project manager for a real-estate development company. Which of these is NOT a responsibility of hers as project manager?
  1. Delivering the project on time, within established fiscal parameters and to specification.
  2. Managing and directing project staff, suppliers, and project stakeholders.
  3. Reviewing the performance standards for team members.
  4. Undertaking the activities required to initiate, plan, execute, and close the project successfully.
Explanation
Answer: C - Reviewing the performance standards for team members is not a responsibility of the project manager. She may want to provide suggestions for input or development of standards, but she is not required to review their performance standards.