Regionally sourced materials takes into account of the amount of a building's material that have gone through all of the following processes except:
  1. extraction
  2. processing
  3. manufacturing
  4. disposal
Explanation
Answer: D - Disposal is NOT one of the factors taken into account when considering regionally sourced materials. Regional materials is the amount of a building's materials that are extracted, processed, and manufactured close to a project site, expressed as a percentage of the total materials cost.