Recommissioning, along with occupant surveying (via a post-occupancy evaluation), is recommended to take place at regular intervals in which phase of the building lifecycle?
  1. Occupancy
  2. Construction
  3. Certificate of occupancy
  4. Sale
Explanation
Answer - A - During the occupancy phase, recommissioning, along with occupant surveying, is recommended. Occupancy occurs after the certificate of occupancy has been received and is continued throughout the life of the building. During occupancy, periodic maintenance such as recommissioning must occur to ensure the building is running optimally and pre-empt any major systemic issues