Project teams should allow a minimum of ________ days for the flush-out period.
  1. 7
  2. 10
  3. 14
  4. 16
Explanation
Answer - C - Project teams should allow a minimum of 14 days for the flush-out period. Flush-out is the operation of mechanical systems for a minimum of two weeks using 100% outside air at the end of construction and prior to building occupancy to ensure safe indoor air quality.