Project team members are allowed to submit supporting LEED Documentation for a project during the following construction phase(s):
  1. predesign
  2. design
  3. construction
  4. design and construction
Explanation
Answer: D - Project team members are allowed to submit LEED Documentation for a project during the design and construction phase. In both phases, documentations should be assembled and upon USGBC's review will be provided a response with "anticipated", "denied" or "achieved".