Organizing flow is typically done with the critical path method and value stream mapping. Which of the following would NOT be included in the benefits of the critical path method when organizing flow?
  1. The ability to acquire resources.
  2. The ability to specify individual activities.
  3. The ability to provide a graphical view of a project.
  4. The ability to show activity precedence and interrelations.
Explanation
Answer: A - The critical path method and value stream mapping are used to organize flow. The ability to acquire resources is incorrect and would NOT be included in the benefits of the critical path method when organizing flow. The critical path method cannot be used to acquire a resource. The Gantt chart associated with the critical path method may be able to assign resources, but not an instrument to acquire resources.