Of the following, which is not a project-planning tool?
  1. PERT Chart
  2. GANTT Chart
  3. Pareto Chart
  4. Ishikawa Diagram
Explanation
Answer: C - A Pareto chart is not a project-planning tool.

Key Takeaway: Pareto charts are quality control tools used in identifying those causes, which contribute most to the problems being encountered. Gantt and milestone charts are used to graphically display activities of a project in sequential order and plot them against time. PERT charts are used to schedule, organize, and coordinate tasks within a project.