LEED Credit Interpretation Requests are typically submitted when:
  1. Points are achieved over a specific threshold
  2. An Exemplary Performance credit is achieved
  3. A credit is submitted and rejected for points
  4. There is a conflict between credit requirements
Explanation
Answer - D - When there is a conflict between credit requirements, a LEED Credit Interpretation Request is submitted for clarification. Typically, after submitting the request, a Credit Interpretation Ruling is issued with an explanation and/or approval or rejection of a request.