Jordi Brahms is double checking to make sure he has all the inputs to the Risk Management Planning and Analysis process accounted for. Which of the following is NOT an input to the Risk Management Planning and Analysis process?
  1. PWBS
  2. Risk response plan
  3. Program schedule
  4. Program budget
Explanation
Answer - B - Risk response plan is not an input to the Risk Management Planning and Analysis process.

Key Takeaway: The Risk Management Planning and Analysis process includes identifying program risks, a detailed risk analysis (both qualitative and quantitative), and effective risk-response planning. The most common risks arise from the program schedule and program cost. Because of this, the key input items for the Risk Management Planning and Analysis process are the program schedule, the PWBS, and the program budget.