Six Sigma Green Belt Exam Prep

Category - Six Sigma Green Belt

In DMAIC project methodology, the ‘I’ refers to the following:
  1. integrate current products
  2. integrate future products
  3. improve current processes
  4. improve future processes
Explanation
Answer: C - In DMAIC project methodology, the ‘I’ refers to the improvement of current processes.
Key Takeaway: Improving current processes involves the use of data analysis techniques or observation methods. In DMAIC project methodology, improving current processes is an important prerequisite for optimizing quality and productivity as well as developing future processes.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz