In business process improvement, managers are encouraged to apply the PDCA problem-solving process. What does the C stand for in PDCA?
  1. control
  2. customize
  3. check
  4. condition
Explanation
Answer: C - The C stands for Check.

Key Takeaway: The PDCA process in problem-solving stands for Plan-Do-Check-Act. The goal of PDCA is to use the scientific method to plan a course of action and then implement it. Once implemented, it is important to check if it has been effective. The final part is to analyze the effectiveness of the plan.