In a project, the construction documents phase occurs before ______ and after ______.
  1. Construction administration; construction
  2. Construction; construction administration
  3. Construction; bidding
  4. Construction administration; schematic design
Explanation
Answer - D - In a project, the construction documents phase occurs before construction administration and after schematic design. In schematic design, the project team members explore several design options and alternatives to establish the scope of work, followed by the work being documented in detail so that construction can take place, and finally, construction administration.