During the development of which document would you be likely to use the POTI model?
  1. Blueprint
  2. Business Case
  3. Programme Mandate
  4. Quality Management Strategy
Explanation
Answer - A - You would be likely to use the POTI model when developing the Blueprint.

Key Takeaway: The POTI (Processes, Organisation, Technology, Information) model sets a high level scope of what must be included and integrated in an effective Blueprint.