During the construction administration phase, which one of the following tasks is performed?
  1. Commissioning
  2. Bidding
  3. Construction documents
  4. Costs are established
Explanation
Answer - A - During the construction administration phase is when the actual construction of the project and commissioning takes place, typically once the systems have been installed and are operable. Commissioning (Cx) is the process of verifying and documenting that a building and all of its systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the owner’s project requirements.