PMI PMP Project Management

Category - HR Management

A Staffing Management Plan is comprised of all the following EXCEPT:
  1. Addresses safety hazards and how staff members are to deal with them
  2. Outlines training needs of team members
  3. Indicates how resources will be obtained
  4. Addresses how to deal with belligerent sponsors
  5. All of the above
Explanation
Answer: d - The Staff Management Plan does not address d, although we could use a plan now and again on how to deal with upset Sponsors (perhaps in another manual). The Plan does effectively address the other concerns: safety hazards, training needs and how to obtain resources.

Key Take Away: Staff Management Plans may prove to be effective tools for some project managers that deal with a large number of new or outsourced team members. Because of the prevalence of outsourcing, we thought it worth highlighting here.
Was this helpful? Upvote!