A project team member is detailing the specifics in planning the air conditioning systems within a building. This project is in the ________ phase of construction.
  1. Schematic design
  2. Design development
  3. Construction documents
  4. Construction administration
Explanation
Answer - C - During the construction documents phase, one carries the design into the detail level for all spaces, systems, and materials so that construction can take place. After the design options have been explored and the process of spatial refinement has been completed, the construction documents phase begins.