A project manager has multiple lean projects she manages concurrently. Why would she employ a corrective action system?
  1. To ensure implementation and establish that timelines are followed and sustainment is enacted.
  2. To ensure team members complete assigned team tasks.
  3. To ensure documentation for compliance purposes.
  4. To eliminate sustainment activities.
Explanation
Answer: A - She would employ a corrective action system to ensure implementation and establish that timelines are followed and sustainment is enacted for lean initiatives.