A company offers a limited budget of $0.125 million to design its new clothing manufacturing machines. This process is referred to as:
  1. design to efficiency
  2. design to efficacy
  3. design to cost
  4. design to style
Explanation
Answer: C - This process is referred to as design to cost.

Key Takeaway: Design to cost is a process whereby an organization limits design options to the available budget. Cost, in this instance, is added to the planning stage as an independent design parameter that limits the number of options available.