51.You are the CEO receiving a report for a crucial, high visibility project, The Omega Project. Your PM reports that Omega’s schedule performance index (SPI) is sitting at 1.28 and cost performance index (CPI) at 0.88. What would you say describes Omega’s status?
52.Lance Uppercut has been on the job for one week as a Project Manager. He’s been advised to safeguard confidential information at all cost. One day, he’s approached by a coworker who claims to need confidential information that Lance is privy to. What is Lance’s best option as to what to do?
54.This is based on a real scenario at a Japanese investment bank. You have discovered a major complex case of international fraud at the company in the course of executing a project. You have reported it to your manager and were not satisfied by his lack of response. What should your NEXT action be?