A WBS can be one of your most used tools, when used correctly; however, what will a WBS not show you?
  1. Dependencies
  2. Hierarchy
  3. A breakdown of each work package
  4. All the work involved in that project
  5. A WBS will show you all of these things.
Explanation
Answer: a - It’s important to remember that a WBS does not show dependencies.

A WBS does show hierarchy, a breakdown of each work package, and all the work that involved in that particular project.

Key Take Away: It’s important to be equipped with and utilize a WBS to optimize team member performance. Utilizing a detailed WBS helps keep the BS at the door.