According to the DRI Professional Practices, what are the 3 criteria to be used to identify alternative facility and offsite requirements?
  1. Facilities
  2. Cost
  3. Communicatons
  4. Personnel
  5. Utilities
Explanation
Answer: A, C, E - Facilities, communications and utilities are the three criteria for identifying alternative facility and offsite requirements.

Key Takeaway: This is a somewhat tricky question, but the professional practices are focused on the characteristics of the physical site at this point in the process.