True or false: Business continuity planning should be run as a committee of leaders across the organization.
  1. True
  2. False
Explanation
Answer: False. The business continuity planning process should be run as a project and receive project funding.

Key Takeaway: A committee approach is not best practices because it does not ensure the necessary funding and management attention is devoted to the BCP process.