Which of the following elements are typically included on the Erosion and Sediment Control Plan of a construction site?
  1. Site drawing with existing and proposed conditions
  2. Standard details of each erosion and sediment control best management plan (BMP) proposed for use
  3. BMP inspection and maintenance schedule
  4. All of the above.
Explanation
Answer: D - All of the elements listed are typically included on an Erosion and Sediment Control Plan. Local ordinances set the requirements for controlling stormwater runoff from construction sites that may cause soil erosion and sedimentation in downstream waterways. Local ordinances are required to be developed under the U.S. Environmental Protection Agency’s National Pollutant Discharge Elimination System program.