The Concrete Reinforcing Steel Institute (CRSI) recommends that a reinforcing bar (rebar) inspection program be established for all construction projects where reinforcing bars are used. An appropriate checklist for rebar inspection is recommended that includes which of the following items, in addition to those listed below?

Construction schedule

Certified mill test and/or bar coating report

Material shipment schedule

Potential concerns (possible discrepancies, drawing errors)

Critical tolerances

Periodic meeting schedule

  1. Independent testing laboratory reports
  2. Approved placing drawings
  3. A. and B.
  4. None of the above
Explanation

Answer: C - An appropriate checklist for rebar inspection is recommended that includes the listed items, independent testing laboratory reports, and approved placing drawings. CRSI recommends that a checklist procedure and the minimum requirements for rebar acceptance should be established during the pre-construction conference. These quality control measures will help to ensure that the rebar used will meet specific material standards and the project owner’s requirements.

Was this helpful? Upvote!