Zed is getting ready to perform the Develop Program Team process. The output that Zed can expect from this process includes:
  1. Updates to training records and staffing management plan
  2. Performance assessment and improvements
  3. Staffing management plan and training records
  4. Performance assessment and training plan
Explanation
Answer - B - Performance assessment and improvements are outputs of the Develop Program Team process.

Key Takeaway: The program team is the team that is ultimately responsible for developing the benefits at the program level. Largely, the program team is broken into the program manager, who is responsible for overall program management, and the program team members who perform the individual program activities. The team is assessed during the Develop Program Team process, with the goal of increasing the performance of the team and its individual members. The outputs of this process are the performance assessment and improvements.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz