In which phase is a program closed?
  1. Phase three
  2. Phase five
  3. Phase six
  4. Phase seven
Explanation
Answer - B - A program is closed in phase five.

Key Takeaway: Phase five, closing the program, can only happen after the last phase gate review (G4), meaning the program is qualified to exit phase four. The purpose of phase five is to disband, dismantle the program infrastructure, and transition any necessary material and information from the program into ongoing operations, based upon Transition Planning.