Terry is managing a project at a top construction firm. Her project team includes Tammy and Sal. She’s also in constant contact with Burt (her client), Ben (her Direct Manager) and Peter (PMO Officer). Who are the stakeholders in this project?
  1. Terry, Burt
  2. Terry, Burt, Tammy, Sal
  3. Burt, Peter
  4. Terry, Tammy, Sal, Burt, Ben, Peter
  5. Terry, Tammy
Explanation
Answer: d - Stakeholders include the Project Manager, other members of the Project Team, the Client, Sponsor, and anyone from the PMO. Therefore, d is the most comprehensive answer in this case.

Key Take Away: In crucial decision-making moments, it’s important to keep in mind those people who are your project’s Stakeholders. Being able to identify which roles they may fall into is a key step.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz