Which project management technique analyzes tasks and the minimum amount of time that is required to complete each task and the entire project?
  1. Six Sigma
  2. Monte Carlo Technique
  3. Logic Network
  4. Program Evaluation and Review Technique
Explanation
Answer: D - The Program Evaluation and Review project management technique analyzes tasks and the minimum amount of time that is required to complete each task and the entire project. A logic network maps the sequence of activities over time and identifies milestones along the way to project completion. The Monte Carlo technique, or simulation, is used to determine possible outcomes and costs that result from complex projects.

Category: Strategic management and technology - Managing projects