Which of the listed elements is NOT included in the base elements of a project charter?
  1. Analysis of the problem.
  2. The project deliverables.
  3. Communication and status reporting processes.
  4. Responsibilities of team members.
Explanation
Answer: A - An analysis of the problem is NOT included in the base elements of a project charter. The project charter tells the project purpose, scope, deliverables, responsibilities, executive sponsor, project sponsor, roles, issue escalation procedures, implementation plans, milestones, major assumptions, and risks.