PMI PMP Project Manager Certification

Category - Time Management

Which of the following would be the most useful input to a network diagram?
  1. Work breakdown structure
  2. Project scope statement
  3. Sequence of activities
  4. PERT
  5. Parkinson’s Law
Explanation
Answer: Since the network diagram shows the sequence of events that will take place in a project, the most helpful item to have would be a sequence of activities.

Key takeaway: For those of you taking the PMI Exam, there are questions where there a number of items that would seem nice to have and are mandatory for the project, but one is clearly the best for the exact task you are doing.