PMI PMP Project Manager Certification

Category - Project Processes

Which of the following tasks could be part of the Scope Control process? Select all that apply:
  1. Adjust the scope baseline
  2. Re-planning
  3. Analyze variances
  4. Maintain issue log
  5. Maintain communications management plan
Explanation
Answer: A, B, C - Updating the scope baseline, re-planning and analyze variances fall under the Scope Control processes.

Maintain issue log and maintain communications management plan are all processes under Manage Stakeholders. These are hard ones, so we’re including them multiple times in the answers.

Key takeaway: Managing scope should be on your mind all the time as a project manager.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz