Which of the following project life cycle stages includes the development of the goals, deliverables, and project charter?
  1. Termination stage of the project life cycle.
  2. Planning stage of the project life cycle.
  3. Conceptualization stage of the project life cycle.
  4. Execution stage of the project life cycle.
Explanation
Answer: C - The conceptualization stage of the project life cycle stages includes the development of the goals, deliverables, and project charter. Termination is the sustainability plan, transferring the product to the customer, resources reassignment, and project close out. Planning includes creating the schedule, mapping the system, and identifying the project tasks. Execution is the actual work of the project.