PMI PMP Project Manager Certification

Category - Scope Management

Which of the following is a tool to analyze whether the project is on schedule?
  1. Project charter
  2. Work Breakdown Structure
  3. WBS Dictionary
  4. Hierarchical project matrix
  5. Variance analysis
Explanation
Answer: E - Variance analysis measures a project against what was planned in terms of time and budget.

Key Takeaway: A variance analysis should be run against a project baseline and constantly updated to include any scope changes.