When visually managing the flow of a process, what is the primary goal of a visual project board?
  1. To provide the status and progress of a project.
  2. To show the team members and charter for a project.
  3. To show the project timeline.
  4. To show the return on investment for the project.
Explanation
Answer: A - When visually managing the flow of a process, the primary goal of a visual project board is to show the status and progress of a project. The goal is to provide a brief visual update to management and employees of the work area impacted by a project. It allows them to see what areas may need improvement.