Select all that apply - a WBS dictionary can contain which of the following:
  1. Interdependencies
  2. Approval criteria
  3. Detailed description
  4. Numeric identifier
  5. Gold plating
Explanation
Answer: A, B, C and D - What is contained in the WBS dictionary is at the discretion of the project manager, but a good entry will have a numeric identifier corresponding to the WBS, a description with appropriate detail, the requirements for acceptance/approval and interdependencies.

Key Takeaway: We think of the a WBS entry as something you could hand to someone who is going to take on the task as an info sheet on that specific work package.