PMI PMP Project Manager Certification

Category - Time Management

Once the Project Manager completes the schedule network analysis, the risk that is identified must be cared for within the project schedule. What type of formats are permissible ways to show logical relationships?
  1. Network Diagram
  2. Project Scope Statement
  3. Progress Reports
  4. Critical Path Baseline
  5. PERT
Explanation
Answer: A - The project schedule can be shown in network diagram format. In addition, the bar or milestone chart is also an acceptable way to indicate possible dependencies. Risk must be indicated in the project plan. Once risk is planned for, it is no longer risk, but an issue that is managed through.

Key Takeaway: Having a schedule network analysis available will allow the Project Manager to monitor the status of the project. At any given moment, the Project Manager can intelligently explain and give current status and what is needed to complete the project. Once any risk to the original plan is found, the Project Manager can re-work the plan based on the needs that are revealed.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz