PMI PMP Project Manager Certification

Category - Time Management

It was Bob’s job to figure out the dependencies among the schedule activities. Bob discovered that all these dependencies are of type finish-to-start. Now Bob needs a network diagramming method to display these dependencies. Which should he use?
  1. Arrow diagramming method only
  2. Precedence diagramming method only
  3. Either the PDM or the ADM
  4. Critical diagramming method
Explanation
Answer - C - Bob can use either the PDM or the ADM.
Key Takeaway: The Arrow diagramming method can only be used to display finish-to-start dependencies. The Precedence diagramming method can be used to display any type of dependencies: finish-to-finish, start-to-start, start-to-finish, and finish-to-start.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz