PgMP Program Management

Category - Domain 3

Integration Management includes which program Planning processes?
  1. Develop Program Management Plan, Transition Planning, and Plan Program Contracting
  2. Develop Program Management Plan, Transition Planning, and Resource Planning
  3. Develop Program Management Plan, Integrated Change Control, and Resource Planning
  4. Develop Program Management Plan, Quality Planning, and Resource Planning
Explanation
Answer - B - Develop Program Management Plan, Transition Planning, and Resource Planning are included in integration management.

Key Takeaway: Integration Management includes the following program Planning processes: Develop Program Management Plan, Transition Planning, Resource Planning, and Interface Planning. Quality Planning belongs to Quality Management. Plan Program Contracting belongs to Procurement Management. Integrated Change Control belongs to the Executing process group.