Developing a Business Continuity Plan review schedule is part of which stage of BCP planning?
  1. Readiness
  2. Prevention
  3. Response
  4. Evaluation and Maintenance
Explanation
Answer: D - The Evaluation and Maintenance stage of the Business Continuity Plan development includes developing a review schedule to ensure that the BCP stays current.

Key Takeaway: By reviewing the Business Continuity Plan on a regularly scheduled basis, the information will remain current and up-to-date. This review schedule should be planned in advance as part of the Evaluation and Maintenance stage of initial BCP planning.