All of the following tools can be used to determine the scope of a lean project EXCEPT?
  1. A product analysis.
  2. An alternatives identification.
  3. A data collection plan.
  4. A stakeholder analysis.
Explanation
Answer: C - A product analysis, alternatives identification, and a stakeholder analysis can all be used to determine the scope of a lean project. A data collection plan is not a tool used in determining the project scope. The data collection plan houses information relative to the process or service which needs to be measured to improve.