CAPM Project Management Exam Prep

Category - HR Management

A responsibility assignment chart is used to clarify team members’ responsibilities. What does this chart NOT show?

  1. Team member names
  2. Tasks
  3. Primary and secondary responsibilities
  4. Time frames to complete task
  5. All of the above
Explanation

Answer: D - We know that was a bit easy, but they can’t ALL be hard. The responsibility assignment shows all of those items noted above, EXCEPT time frames to complete the tasks.

Key Take Away: When utilizing various tools and charts, it’s important to keep in mind the needs of your team members. Project Managers may be very internally organized, but it may not translate out to the team that way UNLESS you use tools that will concretely and effectively help organize the rest of the team.

Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz