A Foreign Service Officer facilities manager has decided to hire a landscaping company to maintain the embassy grounds and has developed a statement of work (SOW) to fulfill the requirement phase of the contract life cycle. Which of the following steps should be taken next?
  1. Award
  2. Requisition
  3. Procurement
  4. Solicitation
Explanation
Answer: B - Requisition.